QuickSigner › Contract templates › Change order
A one-page change order form that records a change to a signed contract: what changes, what it adds to or deducts from the price, and how many days it adds to or deducts from the schedule. It comes with a change order log and works for construction, trade and service contracts.
No account, no email address. Free to download and edit. See all 3 pages
3 pages · PDF and WordA change order is a signed document that changes the scope, the price or the schedule of a contract that is already in force.
The original contract stays in place. The change order adds to it: it describes the work that is added, removed or changed, states the amount added to or deducted from the contract price, and states the days added to or deducted from the completion date. Both parties sign it, and from that moment the contract reads as changed.
Change orders are standard in construction, where the owner and the contractor sign one for every change to the work. The same form serves any project contract with a fixed scope: an office fit-out, an equipment installation, a software build or a marketing project.
This template puts the whole change on one page, so the person who approves it sees the old price, the change and the new price together. Page 2 is a log that lists every change order on the contract, so you always know the current price and the current completion date.
| Change order | Contract amendment | New statement of work | |
|---|---|---|---|
| Use it for | A change to scope, price or time inside an existing project | A change to the terms of the contract itself, such as payment terms or liability | A new project under the same master agreement |
| Length | One page | One page or more | Several pages |
| How often | Many times in one project | Rarely | Once for each project |
| Template | This page | Not published yet | Statement of work template |
Use it each time the work, the price or the completion date of a signed contract changes.
Five numbered sections and two signature blocks on page 1, a change order log on page 2 and a page of notes.
| Section | What it does | What you fill in |
|---|---|---|
| Header table | Links the change order to one contract and one project. | Change order number, date, project, location, contract title and date, who requested the change, client, contractor |
| 1. Description of the change | States the work added, removed or changed. | The description and the drawings, specifications or quotes attached |
| 2. Reason for the change | Records why the change is made. | One tick: client request, unforeseen condition, design change, code requirement or other |
| 3. Change to the Contract price | Shows the price before the change, the amount added or deducted and the new price. | Price basis (fixed amount, unit prices, or time and materials with a cap) and five amounts |
| 4. Change to the Contract time | Shows the completion date before the change, the days added or deducted and the new date. | Two dates and a number of days, or a tick for no change |
| 5. Terms | No changed work before both parties sign. The amounts and days are the full adjustment for this change. Payment follows the contract. All other contract terms stay in effect. Electronic signatures and counterparts are allowed. | Nothing |
| Signatures | Client and contractor accept the change. | Signature, name, title and date for each party |
| Change order log (page 2) | Lists every change order on the contract in the order signed, with the running contract price and completion date. | One row for each change order, 16 rows available |
| Notes (page 3) | Ten notes on completing the form. | Nothing. Delete the page before you sign. |
All 3 pages of the template, exactly as you download them.
Seven steps, from the contract clause to the log.
An office fit-out where the client adds six power outlets after the contract is signed.
| Blank | Where | Example entry |
|---|---|---|
| Change order no. | Header table | 2 |
| Contract and date | Header table | Office Fit-Out Agreement, September 14, 2026 |
| Client / Contractor | Header table | Northwind Trading Ltd / Acme Studio LLC |
| Description | Section 1 | Supply and install six duplex power outlets in meeting room 2, per marked-up drawing E-102 rev B and quote Q-318 (attached) |
| Reason | Section 2 | Client request |
| Original Contract price | Section 3 | $48,000 |
| Net change by previous change orders | Section 3 | $1,500 |
| Contract price before this Change Order | Section 3 | $49,500 |
| This Change Order adds | Section 3 | $2,350 |
| New Contract price | Section 3 | $51,850 |
| Completion date before / days / new date | Section 4 | December 11, 2026 / adds 3 days / December 14, 2026 |
The names and amounts are examples. The price check is simple: $48,000 + $1,500 = $49,500, and $49,500 + $2,350 = $51,850.
Each one turns an agreed change into a payment dispute.
The contractor does the extra work on a spoken instruction and invoices later. The client disputes the price or says the work was never ordered.
Fix: Section 5(a) of the template says the changed work starts only after both parties sign. Sign first.
The price is agreed and nobody writes down the effect on the completion date. Weeks later one side claims a delay.
Fix: complete Section 4 every time. If the date does not move, tick “makes no change” and write 0 days.
“Extra electrical work” does not say what is included. The parties later disagree on what the amount covers.
Fix: state quantities and locations, and attach the drawing or the quote with its number and date.
A site supervisor signs for the client and the client’s office refuses to pay, because the supervisor had no authority to change the price.
Fix: check who may sign changes under the contract and have that person sign.
After several change orders nobody is sure of the current contract price. Invoices and the final account do not match.
Fix: fill in the full price table on each form and keep the log on page 2 up to date.
Many contracts require written notice of a claim for extra cost or time within a fixed number of days. A late change order can be refused for that reason alone.
Fix: read the change clause first and send the notice it requires on time.
General information with links to the official sources. Contract and construction law differ by state.
A change order changes an existing contract, so both parties must agree to it. Your contract’s own change clause sets the procedure: who may order a change, in what form and within what time. For contracts for the sale of goods, the Uniform Commercial Code states that an agreement modifying a contract needs no consideration to be binding, and that a signed contract which excludes modification except by a signed writing cannot otherwise be modified, although an attempt at modification that does not meet that requirement can operate as a waiver. See UCC § 2-209. Service and construction contracts follow state contract law.
Some states set rules for change orders on residential work. In California, an extra work or change order is not enforceable against the buyer unless it sets forth the scope of work, the amount to be added to or subtracted from the contract, and the effect on progress payments or the completion date. The buyer may not require the contractor to perform extra or change-order work without written authorization. See California Business and Professions Code § 7159.6. Sections 1, 3 and 4 of the template record those three points. Check the rules of the state where the work is done.
On federal fixed-price construction contracts above the simplified acquisition threshold, the Contracting Officer may order changes within the general scope of the contract by a written order designated as a change order. If a change increases or decreases the contractor’s cost or time, the Contracting Officer makes an equitable adjustment and modifies the contract in writing. The contractor must assert its right to an adjustment within 30 days after it receives the written change order. See FAR 52.243-4, Changes. Federal agencies use their own forms, so this template is for private contracts and for subcontracts.
Under the federal ESIGN Act, a signature or contract may not be denied legal effect solely because it is in electronic form. See 15 U.S.C. § 7001. The Uniform Electronic Transactions Act has been adopted by 49 states and the District of Columbia, and New York has a similar statute of its own. Section 5(e) of the template states that the change order may be signed by electronic signature.
Save the completed document as a PDF, upload it and add the signers. The three steps are shown in the real QuickSigner app (Professional plan), with a sample service agreement.
Upload the completed PDF, add the person who signs for each party, and place a signature field in each signature block. Then press Send.

Each signer opens the link and goes straight to the document, on a phone or a computer. They draw, type or upload a signature and finish in one tap.

When the last signature lands, download the signed document as a sealed PDF, with its completion certificate and event log.

Short answers to the questions people ask before they sign one.
A change order is a signed document that changes the scope, the price or the schedule of a contract that is already in force. The original contract stays in effect, as changed by the change order.
Usually the contractor prepares it, because the contractor prices the change. The client and the contractor both sign. On each side, the signer must have authority to change the contract price.
The contract it changes, a description of the change, the amount added to or deducted from the price, the days added to or deducted from the schedule, and the signatures of both parties. The template also records the reason and the new contract price and completion date.
Yes, once both parties sign it. It is a modification of the contract and has the same force as the contract. Your contract may set extra conditions, such as a notice period, so read its change clause.
Yes. A change order that removes work is often called a deductive change order. In Section 3 of the template, tick “deducts” and enter the amount. The new contract price is lower than the price before.
A change order changes the work, the price or the time inside a project. A contract amendment changes the terms of the contract itself, such as payment terms, liability or governing law.
Yes, if the scope or the completion date changes. Enter $0 in Section 3 and complete Section 4. A signed record prevents a later claim for money or time.
The contractor may not be paid for it. Many contracts require a signed change order before extra work, and some state laws make an unwritten change order on home improvement work unenforceable against the homeowner.
Yes. US law gives electronic signatures the same legal effect as handwritten ones for contracts like this, and Section 5(e) of the template allows them. Upload the completed PDF to QuickSigner, add the signers and send it. Each signer signs from a link, with no account.
The template is free to download in PDF and Word. You need no account and no email address. You need a QuickSigner account only to sign or send the document online. The Free plan covers 5 documents a month and needs no credit card.
No credit card. The client signs from a link, with no account and no app. Paid plans start with a 14-day free trial.