Free business template

Change order template

A one-page change order form that records a change to a signed contract: what changes, what it adds to or deducts from the price, and how many days it adds to or deducts from the schedule. It comes with a change order log and works for construction, trade and service contracts.

No account, no email address. Free to download and edit. See all 3 pages

Change order template, page 1: contract details, description of the change, price and time tables, signatures3 pages · PDF and Word
Page 1 of 3. See every page
Ready to sign?

Send it with QuickSigner and get it signed in seconds.

  • PAdES‑sealed PDF
  • Adobe‑trusted (AATL) certificate
  • ISO/IEC 27001:2022 certified
  • ESIGN, UETA and eIDAS
Send it for signature free →Free plan · No credit card
Format
PDF and Word (.docx), US Letter
Length
3 pages: form, log, notes
Contents
5 sections, price and time tables, change order log
Works under
Any signed contract with a price and a completion date
Signed by
Client and contractor
Price
Free, no account needed
Written and reviewed by
QuickSigner Team
Last reviewed
November 18, 2026
Definition

What is a change order?

A change order is a signed document that changes the scope, the price or the schedule of a contract that is already in force.

The original contract stays in place. The change order adds to it: it describes the work that is added, removed or changed, states the amount added to or deducted from the contract price, and states the days added to or deducted from the completion date. Both parties sign it, and from that moment the contract reads as changed.

Change orders are standard in construction, where the owner and the contractor sign one for every change to the work. The same form serves any project contract with a fixed scope: an office fit-out, an equipment installation, a software build or a marketing project.

This template puts the whole change on one page, so the person who approves it sees the old price, the change and the new price together. Page 2 is a log that lists every change order on the contract, so you always know the current price and the current completion date.

Change orderContract amendmentNew statement of work
Use it forA change to scope, price or time inside an existing projectA change to the terms of the contract itself, such as payment terms or liabilityA new project under the same master agreement
LengthOne pageOne page or moreSeveral pages
How oftenMany times in one projectRarelyOnce for each project
TemplateThis pageNot published yetStatement of work template
Fit

When to use a change order

Use it each time the work, the price or the completion date of a signed contract changes.

Use it when

  • The client asks for work that the contract does not include.
  • Work is removed from the contract and the price goes down.
  • A condition found on site makes the planned work impossible or more expensive.
  • A design, a specification or a material changes after signing.
  • The completion date moves, with or without a change in price.
  • You are a contractor and must pass a client change down to a subcontractor.

Use something else when

  • No contract is signed yet. Start with a service agreement or a subcontractor agreement.
  • The work is a new project under a master agreement. Sign a new statement of work.
  • You want to change contract terms such as liability, confidentiality or governing law. Sign a contract amendment.
  • The change is so large that it replaces the original scope. Sign a new contract.
  • You are pricing or ordering work that has no contract yet. Use a quote or a purchase order.
Contents

What the template contains

Five numbered sections and two signature blocks on page 1, a change order log on page 2 and a page of notes.

SectionWhat it doesWhat you fill in
Header tableLinks the change order to one contract and one project.Change order number, date, project, location, contract title and date, who requested the change, client, contractor
1. Description of the changeStates the work added, removed or changed.The description and the drawings, specifications or quotes attached
2. Reason for the changeRecords why the change is made.One tick: client request, unforeseen condition, design change, code requirement or other
3. Change to the Contract priceShows the price before the change, the amount added or deducted and the new price.Price basis (fixed amount, unit prices, or time and materials with a cap) and five amounts
4. Change to the Contract timeShows the completion date before the change, the days added or deducted and the new date.Two dates and a number of days, or a tick for no change
5. TermsNo changed work before both parties sign. The amounts and days are the full adjustment for this change. Payment follows the contract. All other contract terms stay in effect. Electronic signatures and counterparts are allowed.Nothing
SignaturesClient and contractor accept the change.Signature, name, title and date for each party
Change order log (page 2)Lists every change order on the contract in the order signed, with the running contract price and completion date.One row for each change order, 16 rows available
Notes (page 3)Ten notes on completing the form.Nothing. Delete the page before you sign.
Preview

See every page

All 3 pages of the template, exactly as you download them.

Step by step

How to fill in a change order

Seven steps, from the contract clause to the log.

  1. Read the change clause of your contract. It may require written notice within a set number of days, a particular form or a particular signer. That clause applies in addition to this form.
  2. Number the change order and identify the contract. Number change orders in sequence, starting at 1 for each contract. Enter the contract title, its date and the parties exactly as signed.
  3. Describe the change. Write it so that a person who was not in the discussion could price it and carry it out. Refer to drawing, specification or quote numbers and attach them.
  4. Tick the reason. The reason matters later, when someone asks who caused the extra cost.
  5. Complete the price table from top to bottom. Original price, net change by previous change orders, price before this change order, the amount this change order adds or deducts, and the new contract price.
  6. Complete the time table. Enter the completion date before the change, the days added or deducted and the new date. If the date does not move, tick “makes no change” and write 0 days.
  7. Sign before the changed work starts, then update the log. Both parties sign. Enter the change order in the log on page 2 and delete the notes page.

A filled-in example

An office fit-out where the client adds six power outlets after the contract is signed.

BlankWhereExample entry
Change order no.Header table2
Contract and dateHeader tableOffice Fit-Out Agreement, September 14, 2026
Client / ContractorHeader tableNorthwind Trading Ltd / Acme Studio LLC
DescriptionSection 1Supply and install six duplex power outlets in meeting room 2, per marked-up drawing E-102 rev B and quote Q-318 (attached)
ReasonSection 2Client request
Original Contract priceSection 3$48,000
Net change by previous change ordersSection 3$1,500
Contract price before this Change OrderSection 3$49,500
This Change Order addsSection 3$2,350
New Contract priceSection 3$51,850
Completion date before / days / new dateSection 4December 11, 2026 / adds 3 days / December 14, 2026

The names and amounts are examples. The price check is simple: $48,000 + $1,500 = $49,500, and $49,500 + $2,350 = $51,850.

Avoid

Six mistakes to avoid

Each one turns an agreed change into a payment dispute.

Starting the work before the signature

The contractor does the extra work on a spoken instruction and invoices later. The client disputes the price or says the work was never ordered.

Fix: Section 5(a) of the template says the changed work starts only after both parties sign. Sign first.

Leaving the time section blank

The price is agreed and nobody writes down the effect on the completion date. Weeks later one side claims a delay.

Fix: complete Section 4 every time. If the date does not move, tick “makes no change” and write 0 days.

A vague description

“Extra electrical work” does not say what is included. The parties later disagree on what the amount covers.

Fix: state quantities and locations, and attach the drawing or the quote with its number and date.

The wrong person signs

A site supervisor signs for the client and the client’s office refuses to pay, because the supervisor had no authority to change the price.

Fix: check who may sign changes under the contract and have that person sign.

No running total

After several change orders nobody is sure of the current contract price. Invoices and the final account do not match.

Fix: fill in the full price table on each form and keep the log on page 2 up to date.

Ignoring the contract’s notice period

Many contracts require written notice of a claim for extra cost or time within a fixed number of days. A late change order can be refused for that reason alone.

Fix: read the change clause first and send the notice it requires on time.

Legal background

What US law says about change orders

General information with links to the official sources. Contract and construction law differ by state.

A change order is a contract modification

A change order changes an existing contract, so both parties must agree to it. Your contract’s own change clause sets the procedure: who may order a change, in what form and within what time. For contracts for the sale of goods, the Uniform Commercial Code states that an agreement modifying a contract needs no consideration to be binding, and that a signed contract which excludes modification except by a signed writing cannot otherwise be modified, although an attempt at modification that does not meet that requirement can operate as a waiver. See UCC § 2-209. Service and construction contracts follow state contract law.

Home improvement work: written change orders can be mandatory

Some states set rules for change orders on residential work. In California, an extra work or change order is not enforceable against the buyer unless it sets forth the scope of work, the amount to be added to or subtracted from the contract, and the effect on progress payments or the completion date. The buyer may not require the contractor to perform extra or change-order work without written authorization. See California Business and Professions Code § 7159.6. Sections 1, 3 and 4 of the template record those three points. Check the rules of the state where the work is done.

Federal construction contracts follow the FAR Changes clause

On federal fixed-price construction contracts above the simplified acquisition threshold, the Contracting Officer may order changes within the general scope of the contract by a written order designated as a change order. If a change increases or decreases the contractor’s cost or time, the Contracting Officer makes an equitable adjustment and modifies the contract in writing. The contractor must assert its right to an adjustment within 30 days after it receives the written change order. See FAR 52.243-4, Changes. Federal agencies use their own forms, so this template is for private contracts and for subcontracts.

Electronic signatures on a change order are valid

Under the federal ESIGN Act, a signature or contract may not be denied legal effect solely because it is in electronic form. See 15 U.S.C. § 7001. The Uniform Electronic Transactions Act has been adopted by 49 states and the District of Columbia, and New York has a similar statute of its own. Section 5(e) of the template states that the change order may be signed by electronic signature.

E‑sign

How to e‑sign it with QuickSigner.

Save the completed document as a PDF, upload it and add the signers. The three steps are shown in the real QuickSigner app (Professional plan), with a sample service agreement.

Step 1 · Send

Upload the document and add the signers

Upload the completed PDF, add the person who signs for each party, and place a signature field in each signature block. Then press Send.

  • The Free plan sends 5 documents a month, with up to 3 signers per sign request
  • Free places signature fields, so type names, titles and dates into the document before you save it
  • On Business, upload the Word file directly and set the signing order
E‑sign it free
app.quicksigner.com/requests/new
QuickSigner new sign request: two signers in order, SMS verification enabled for the first signer, two signatures and two dates placed
Step 2 · Sign

The other party signs from the e‑mail link

Each signer opens the link and goes straight to the document, on a phone or a computer. They draw, type or upload a signature and finish in one tap.

  • No account, no app and no fee for the signer
  • In signing order, the next person is notified as soon as the previous one has signed (Business and Professional)
  • Signed 37 seconds after sending, in an independent hands‑on test
How signing works →
QuickSigner on a phone: the provider has already signed and the client is asked to sign
Step 3 · Track

Download the sealed PDF

When the last signature lands, download the signed document as a sealed PDF, with its completion certificate and event log.

  • AATL document sealing on every plan: any change made after signing is detected
  • An event log of each opening, IP, device, consent and field signed
  • Legally binding under ESIGN, UETA and eIDAS
See plans and pricing →
app.quicksigner.com/requests/sent
QuickSigner sent documents dashboard: agreements with status Completed or In Progress, sent dates and download buttons
FAQ

Change order questions

Short answers to the questions people ask before they sign one.

What is a change order?

A change order is a signed document that changes the scope, the price or the schedule of a contract that is already in force. The original contract stays in effect, as changed by the change order.

Who prepares and who signs a change order?

Usually the contractor prepares it, because the contractor prices the change. The client and the contractor both sign. On each side, the signer must have authority to change the contract price.

What must a change order include?

The contract it changes, a description of the change, the amount added to or deducted from the price, the days added to or deducted from the schedule, and the signatures of both parties. The template also records the reason and the new contract price and completion date.

Is a change order legally binding?

Yes, once both parties sign it. It is a modification of the contract and has the same force as the contract. Your contract may set extra conditions, such as a notice period, so read its change clause.

Can a change order reduce the contract price?

Yes. A change order that removes work is often called a deductive change order. In Section 3 of the template, tick “deducts” and enter the amount. The new contract price is lower than the price before.

What is the difference between a change order and a contract amendment?

A change order changes the work, the price or the time inside a project. A contract amendment changes the terms of the contract itself, such as payment terms, liability or governing law.

Do I need a change order if the price does not change?

Yes, if the scope or the completion date changes. Enter $0 in Section 3 and complete Section 4. A signed record prevents a later claim for money or time.

What happens if extra work is done without a change order?

The contractor may not be paid for it. Many contracts require a signed change order before extra work, and some state laws make an unwritten change order on home improvement work unenforceable against the homeowner.

Can I sign a change order electronically?

Yes. US law gives electronic signatures the same legal effect as handwritten ones for contracts like this, and Section 5(e) of the template allows them. Upload the completed PDF to QuickSigner, add the signers and send it. Each signer signs from a link, with no account.

Is the template free, and do I need an account?

The template is free to download in PDF and Word. You need no account and no email address. You need a QuickSigner account only to sign or send the document online. The Free plan covers 5 documents a month and needs no credit card.